Client

:

Kromberg &Schubert


Consultant

:

ZIM


Project duration

:

13 months (2015 - 2016)


Contract

:

General Contractor for civil, mechanical, electrical works including engineering and design works.


Type of construction

:

Steel structure


Description

:

Reinforced concrete and steel columns, space frame roof, sandwich roof and faade panels


Total construction area

:

22,000 m


Total closed area

:

26,000 m